Certus Via company has designed two flyovers: i.e. WD-01 and WD-02 which are part of the eastern bypass of Biała Podlaska. The project was commissioned by the Municipality of Biała Podlaska.
WD-01 – road viaduct over railway line no. 2, is a facility combined steel & ferroconcrete characterized by a lightweight construction of the bridge. The main girders are two tandems of steel plate girders. The flyover is based on solid extreme supports – reinforced concrete abutments and column intermediate supports. It will enable pedestrian and motor- vehicle traffic over the railway tracks to be carried out without collisions.

The parameters of the facility:

  • overall span: 124,0 m
  • span in supports: 122,5 m
  • the overall width of the facility: 13,9m
  • the number of bays: 3
  • span of the main bay: 52,5m

WD-02 – road viaduct over Sidorska Street is a reinforced concrete structure with a typical frame structure and upper reinforced concrete transom. The viaduct is integrated in the road embankment, used to carry out without collisions pedestrian and motor- vehicle traffic over Sidorska Street in Biała Podlaska.

The parameters of the facility:

  • overall span: 14,0m
  • span in supports: 13,5m
  • the overall width of the facility: 14,7m

The Ordering Party

The Ordering Party is The President of Biała Podlaska

Start date and end date

The beginning of design works: January 2017

The completing of design works: August 2017

Contract value:

PLN 27 511 341,94 (gross)